Been awhile since I posted but just a couple updates on LR stadium. We have no material delays forthcoming because Looper construction procured all this before the project even started. This is according to the project manager Matt. Secondly we just approved an extra expenditure of eighty thousand to relocate two huge power generators out of site. Things are in the works to secure funding for some other major projects on campus as well. Spring practice is going good and there is a battle for the qb. Position that seems wide open.
- 2 likes
Leave a comment:
-
Not really, I'm just a realist because I've seen projects like this play out before.
Fact is, I hope that not only the project is completed on time, but it ends up being just as the plans projected, which would by far make it the best looking football stadium in the SAC.
- 1 like
Leave a comment:
-
You have literally tried to come up with any reason possible as to why L-R will not get this project done. That's the point I was making.
- 1 like
Leave a comment:
-
Originally posted by Eagle74 View Post
I don't recall seeing or hearing anything about any substantial amount of snow in Hickory NC, but maybe you can enlighten us.
Leave a comment:
-
Originally posted by Eagle74 View PostI'm confident that it will end up being pretty nice. Unfortunately, the weather delays may end up pushing back the completion date.
Leave a comment:
-
I'm confident that it will end up being pretty nice. Unfortunately, the weather delays may end up pushing back the completion date.
Leave a comment:
-
From the pictures I'm seeing above, LRs stadium is going to be nice. Probably the best in D2.
Leave a comment:
-
Originally posted by BEARS View Post
Yeah you keep saying that the project will be scaled back. But I have yet to hear this from literally anybody else.
fortune.com/.../08/steel-prices-2021-going-up-bubble Steel up over 200%
https://www.prnewswire.com/news-rele...high-price-tag
High prices for concrete and cement until at least mid-2022 (now extended)Last edited by Eagle74; 03-29-2022, 12:42 PM.
Leave a comment:
-
I was watching the recent LR-Queens men's lacrosse game and you could see that some of the concrete risers were being poured for the home side of the new stands. Looks like good progress so far.
Leave a comment:
-
Originally posted by Eagle74 View Postwww.delcompany.com/news/lru-moretz-stadium-east...
Looks like (without any weather or material delays) the scheduled completion date for Moretz Stadium remains as August 2022. Due to highly inflated (and soring) construction materials and labor cost, the project may be scaled back from earlier plans. However, it should still be a vast improvement over the former facilities.